| Project and supplied-system boundary | Intended production scope, automatic-change objective, supplied equipment, integration work, site work and every explicit exclusion | Approved scope drawing and responsibility matrix naming the machine, mold, clamping, transfer, utilities, controls, integration and buyer owners |
|---|
| IMM identity and controlled revision | Exact machine and clamping configuration, serial identity when assigned, control and safety-control revisions, installed options and controlled drawings | Supplier configuration baseline tied to the proposed machine; no generic series label or assumed option |
|---|
| Mold family and revision register | Every mold in automatic-change scope, revision, halves, inserts, base plates, services and any family-specific exception | Released mold schedule and drawings with owners, approval state and open deviations |
|---|
| Mold-changing device identity | Exact device, supplier, model or project identity, control/software revision, transfer modules, staging positions and installed options | Controlled device drawings, manuals, option list and machine-facing interface specification |
|---|
| Change topology, loading side and route | Loading side, transfer direction, single or multiple staging positions, floor or machine-mounted equipment and the controlled path between storage and platens | Final layout, motion-envelope and access review for the identified machine, mold family and guarding arrangement |
|---|
| Platen, machine and guarding envelope | Tie-bar and platen envelope, daylight, mold-area guards, service access, transfer clearances and any temporary or retained obstructions | Linked mold-envelope, mounting and final-cell layout records rather than a copied catalogue maximum |
|---|
| Mold mass, dimensions, center of gravity and orientation | Controlled values and datums for each mold half and complete mold, including orientation and any asymmetric or cantilever condition | Mold-owner drawings and approved handling/load basis reviewed by the responsible machine, device and clamping suppliers |
|---|
| Approved mold-mounting interface record | Reference to the released platen datums, centering, fixing or quick-clamping geometry, support concept and mold-specific compatibility decision | Signed mounting/platen interface record; this page does not replace its dimensional review |
|---|
| Clamping-system identity and configuration | Mechanical, hydraulic or magnetic concept; exact supplier and configuration; machine and mold sides; control location; and project-specific exclusions | Controlled configuration and applicability decision; ISO 23582-1 and EUROMAP 70 or 72 are not generalized beyond magnetic systems |
|---|
| Mold retention and detachment load basis | Supplier-required mold, machine and process inputs affecting retention, sliding, breakaway, nozzle, ejector and other relevant loads | Responsible-party calculations, limits and review record for the actual combination; no universal force or margin is supplied here |
|---|
| Contact, surface and thermal condition | Applicable plate material, thickness, contact area, holes or voids, flatness, contamination condition and temperature envelope for the chosen system | Mold and clamping-supplier requirements plus configured inspection evidence; do not transfer a named system's limits |
|---|
| Support, transfer, staging and parking interface | Support points, rollers or transfer surfaces, anti-drop or retained-state boundaries, staging identity, parking condition and ownership at every handoff | Approved drawings and risk-controlled integration records for each physical state, without publishing a motion sequence |
|---|
| Automatic clamping mechanical interface | Selected project interface, relevant EUROMAP 11 part or another controlled specification, mating equipment, revision and exception list | Supplier-approved mechanical interface record; EUROMAP 11 does not prove implementation or fit by title alone |
|---|
| Ejector coupling and release state | Coupling identity, mating datums, load path, working stroke/force references, confirmed release state and ownership before transfer | Linked ejector interface record and configured coupling evidence; this field does not prescribe a coupling or robot handoff |
|---|
| Energy and media coupling interface | Every electrical, heating, cooling, hydraulic, pneumatic and other mold service; coupling identity; mating side; isolation boundary; labeling and revision | Controlled service schedule, connection drawings and as-built inspection; no EUROMAP 11 connection table is reproduced |
|---|
| IMM-to-MCD electrical interface | Exact EUROMAP 71 version or other controlled project specification, endpoint mating sides, required project functions and documented deviations | Approved interface drawing and implemented function schedule; no standard pinout, voltage or universal timing is copied |
|---|
| IMM-to-MCS electrical interface | For a magnetic system only, exact EUROMAP 70 variant/version or other controlled specification, endpoint configuration, required functions and deviations | Approved machine-to-MCS interface and configuration record; a document name does not prove compatibility or safety |
|---|
| Functional states, permissions and fault ownership | One controlled row per required state, permission, availability condition, loss or fault, naming source, destination, meaning and responsible owner | Project functional specification and observed configured evidence; no universal state machine or recovery instruction |
|---|
| Risk, safety function and validation responsibility | Applicable machine and clamping-system boundaries, risk owner, identified safety functions, required performance basis, design owner and validation owner | Qualified risk, design and validation records for the actual system; this checklist selects no safety function, architecture or performance level |
|---|
| Modes, unexpected start-up, acceptance and change control | Mode ownership, isolation and unexpected-startup boundary, approved FAT/SAT scope, as-built documents, open actions and revalidation triggers | Machine- and site-specific requirements, signed configured evidence and revision-controlled handover; this page is not an operating or test procedure |
|---|