| Machine endpoint identity | Exact IMM, clamping and injection configuration, control/software revision, installed options, serial identity when assigned and controlled drawings | Supplier configuration baseline and revision-controlled machine-side electrical, control and interface records |
|---|
| Robot or handling-device identity | Exact equipment type, supplier, model and controller/software revision, mounting orientation, application and supplied options | Controlled robot/handling-device data, manuals, drawings and option list for the proposed endpoint |
|---|
| Mold, part and interaction identity | Mold revision, cavities, inserts, parts, runners, reject path and every IMM/robot interaction that belongs to the proposed production cell | Controlled mold, part, EOAT and cell sequence requirements with named project owners |
|---|
| Interface family and publication status | Exact document, edition or release-candidate version, applicable machine topology and written reason for the selected architecture | Current official source and a project decision; never reduce this field to 'EUROMAP ready' or 'OPC UA ready' |
|---|
| Hardwired functional interface | Required and optional project functions, connector/cable drawing, endpoint mating sides, labeling and the controlled supplier implementation revision | Approved project signal schedule and interface drawing; this page reproduces no standard pinout or universal sequence |
|---|
| OPC UA role and profile | Client/server and publisher/subscriber roles, selected profiles, namespace/model files, dataset instances, network parameters and software compatibility | Configured endpoint records tied to the exact EUROMAP 79 RC and implemented software revisions |
|---|
| Safety-signal path | Selected hardware path, safety-device boundary, direction, project risk owner, validation owner and interfaces intentionally kept outside the data channel | Qualified risk and validation records for the actual cell; no safety architecture or performance level is supplied by this checklist |
|---|
| Functional state semantics | One row per project state or permission, naming source, destination, asserted and cleared meaning, operating mode and affected equipment | Approved functional specification and configured observation record rather than a copied standard table |
|---|
| Mode, selection and startup boundary | Declared behavior when automatic interaction is requested, selected, unavailable, deselected, switched off or restored | Machine and robot requirements plus configured test evidence for the agreed modes; no operating sequence is prescribed here |
|---|
| Communication loss and stale data | Detection owner, affected permissions, alarm/status evidence, data validity, timeout source and approved recovery responsibility | Controlled software requirements and fault evidence tied to the exact implemented channel and revisions |
|---|
| Mold and movable-platen coordination | Project meanings for mold position, mold-area clearance and any permissions needed before an IMM or robot movement | Controlled layout, motion envelope and functional evidence; no universal order, distance or timing is copied into the page |
|---|
| Ejector, core and additional-axis handoff | Only the axes in project scope, their position evidence, robot permissions, incomplete-state handling and separate mechanical-capability records | Linked ejector/core interface registers and configured coordination evidence; a data state cannot prove stroke, force, torque or clearance |
|---|
| Part, insert, runner and reject tracking | Declared availability, identity, removal/insertion and disposition states, including delayed data, empty cycles and exception ownership | Approved traceability and physical-verification plan; a status value alone does not prove successful handling or quality |
|---|
| Robot, EOAT and mold-area fit | Mounting datum, reach/workspace review, EOAT plus part load basis, approach, mold/ejector clearance and retained-state requirements | Responsible supplier/integrator drawings and calculations for the configured equipment; no OEM example transfers to this project |
|---|
| Utilities, network and downstream scope | Control power, robot power, air, vacuum, EOAT services, network, conveyor, inspection and every buyer/supplier boundary | Final utility and network schedules, interface drawings and responsibility matrix |
|---|
| FAT, SAT, handover and change control | Agreed normal/fault evidence at each stage, exact configurations, witnesses, deviations, retest state, backups, as-built records and recheck triggers | Signed acceptance index and controlled handover set; FAT cannot establish untested final-site conditions |
|---|