| Project and dosing-interface boundary | Intended material-delivery function, included dosing or blending equipment, IMM integration work, upstream/downstream systems, site work, supplier work and explicit exclusions | Approved scope diagram and responsibility matrix naming machine, dosing-system, material-supply, integrator and site owners |
|---|
| Injection molding machine identity | Exact proposed machine, injection-unit and controller configuration, software/option baseline, feed-zone endpoint and responsible machine party | Configuration-specific machine record without implying a NEW ORIENTAL IMM dosing option or implementation |
|---|
| Dosing-system identity and revision | Proposed manufacturer, model/configuration, serial identity when assigned, controller/software revision, device mapping and responsible supplier | Controlled supplier configuration; a generic product family, photograph or interface title is insufficient |
|---|
| Material-component register | Buyer-approved identity and role for every main material, additive, color, regrind or other included component, plus every excluded material stream | Controlled component list tied to recipe aliases, supplier/grade records and the proposed project without publishing a formulation |
|---|
| Material state and handling basis | Relevant physical form, flow questions, moisture/temperature history questions, contamination sensitivity and assumptions requiring material-supplier review | Project material basis and supplier disposition; this checklist prescribes no material preparation or handling condition |
|---|
| Dosing architecture and mode | Supplier-defined batch, continuous or combined topology; gravimetric, volumetric or conveying-only component roles; weighing/mixing stages; and unsupported alternatives | Configuration drawing and functional description for the proposed system rather than a generic method ranking |
|---|
| Mounting and feed-point boundary | Direct machine-throat, machine-adjacent, floor, mezzanine, day-bin or other proposed relationship, final material discharge point, support owner and access boundary | Controlled arrangement drawing and load/access disposition; no adapter, frame or installation dimension is selected here |
|---|
| Upstream and downstream material path | Where each material enters the included subsystem, any loader/dryer/conveyor/day-bin handoff, discharge destination, isolation boundary and owner | Reconciled material-flow diagram that keeps the wider material-supply network on its separate release path |
|---|
| Component and delivery-device mapping | Which hopper, valve, screw, feeder, weigh chamber, mixer or other identified element handles each material component and which elements are optional or absent | Configuration-specific component map; model vocabulary does not prove installed hardware or suitability |
|---|
| Cyclic, batch or continuous relationship | Whether material delivery is shot-synchronous, independently batched, continuous or supplier-defined otherwise, including the initiating/receiving owners and open timing questions | Approved functional narrative and configured observations without prescribing a trigger, duration or sequence |
|---|
| Recipe and dataset ownership | Recipe/dataset identity, revision, component aliases, source of truth, edit/release authority, destination, retention owner and change approval | Controlled recipe/dataset lifecycle record with no formulation or universal transfer workflow published |
|---|
| Quantity and value semantics | Meaning, source, unit family and basis for every required component share, shot-related value, batch value, rate, total, scrap or status record | Field dictionary that distinguishes target, actual, total, reset state, validity and missing value without setting a project number |
|---|
| Functional handshake boundary | Every proposed enable, cycle/dose request, ready, active, complete, inhibit, fault or other function; physical/data path; initiator; receiver; and exclusion | Allowlisted functional matrix and configured observation without publishing a pinout, command order or operating sequence |
|---|
| Companion specification and release | Selected EUROMAP 82.4 / OPC 40082-4 release, namespace/model version, related common-type release, profile/facet scope and any controlled extension | Dated applicability record distinguishing official scope, optional elements, vendor extensions and project assumptions |
|---|
| Endpoint, read, write and method scope | Identified endpoint owner; proposed read/write/method families; business purpose; authorization owner; unsupported functions; and separate hardwired/proprietary paths | Configuration-specific support and test matrix; no node list, address, port, credential, certificate or network design is published |
|---|
| Alarm, fault and disposition ownership | Required state/error meaning, source component, display/record owner, acknowledgement/reset authority, product-disposition owner and escalation boundary | Approved semantic matrix and configured observations; this page sets no alarm value, reset action or fault-recovery method |
|---|
| Utilities, loads and physical responsibility | Configuration-specific services and loads for the included package, site connection points, structural/access ownership and dependencies carried to installation planning | Supplier schedules and approved drawings without a fixed capacity, connection, mounting or utility instruction |
|---|
| Material change and contamination evidence | Which component identities, retained-material locations, segregation risks, inspection records, supplier cleaning references and release owners apply after a material/configuration change | Project-approved evidence index and disposition record; no cleaning, purging, filling or calibration procedure is supplied here |
|---|
| Configured FAT and SAT evidence | Which identities, mappings, material/recipe records, functional states, displayed/recorded values, deviations and as-installed relationships require factory and site observation | Approved FAT/SAT references, dated observations, witnesses, deviations and closure under the separate acceptance programme |
|---|
| As-built handover and release decision | Final equipment/component identities, drawings, software/specification releases, mappings, accepted deviations, open assumptions, owners and recheck triggers | Signed handover index and action register; unanswered compatibility, capability, value or evidence items remain open |
|---|