Layout, rigging and foundation planning starts with the exact configured machine.

Coordinate transport, operating and maintenance envelopes with mold handling, robot and auxiliaries, logistics, the building route, utilities and site-specific structural review.

ANSWER FIRST

Plan the spaces and routes the machine needs—not only its parked footprint.

Option-dependent projections, moving equipment, mold loading and component removal can control the real layout. The released configured drawings must arrive early enough for building, rigging, utility and production-flow review.

Coordinate the physical plan with site utilities
Site release gate
  • Configured GA, transport and support data
  • Mold, robot, auxiliary and service envelopes
  • Building route and temporary-work survey
  • Qualified rigging and structural approvals
  • Controlled as-built and acceptance record
Add site constraints to the RFQ
PLANNING ZONES

Seven zones connect machine drawings to a workable production cell.

This is a coordination checklist. Qualified site, rigging, structural and safety parties control their respective designs.

ZoneCollectCoordinateRelease gate
Configured machine envelopeOverall operating and transport dimensions, masses, center-of-gravity/lift-point data, leveling/support points and option-dependent projectionsReleased general arrangement and transport drawing for the exact configurationDo not scale a brochure image or reuse another model's drawing
Mold handling envelopeMold size/mass, loading direction, lifting device, hook/fork path, door/guard opening and temporary stagingMachine, mold, crane/handling-device and building teamsDemonstrate the complete pick, travel, lower, connect and remove path
Robot and auxiliary envelopeRobot stroke/guards, EOAT, conveyor, dryer/loader, thermal equipment, hoses/cables and access to fill/service pointsFinal cell layout and interference reviewInclude moving and maintenance envelopes, not only parked footprints
Operation and maintenance accessOperator stations, doors/panels, barrel/screw service, pumps/drives, filters, lubrication, guarding and removal pathsMachine instructions plus buyer maintenance task reviewAccess must support the intended task and site safety controls
Material and part logisticsResin delivery, bins, packaging, inspection, rejects, finished goods, forklift/pedestrian routes and housekeepingProduction flow and site traffic planKeep routine logistics clear of service and emergency access
Rigging and building routePort/yard/door/corridor constraints, floor/bridge limits, turns, overheads, crane/fork capacity and temporary worksQualified rigging, structural, logistics and site ownersA machine transport drawing is an input; it is not the approved lift plan
Foundation and servicesMachine support/leveling loads, dynamic information where supplied, floor data, trenches, anchors, drains and utility entry pointsConfigured-machine supplier, qualified structural engineer and site utility ownersFoundation and anchoring design remain site- and configuration-specific
DRAWING REGISTER

Track the file, revision, configuration and approving owner.

Mark preliminary files visibly and replace them in a controlled register when configured drawings are released.

Required recordMinimum content
Configured GA drawingMachine/options identity, revision, operating envelope, service projections and utility entry points
Transport drawingShipping split, transport dimensions/masses, lift points, center-of-gravity information and handling restrictions
Foundation/support drawingSupport/leveling points, loads and anchoring data actually released for the configured machine
Mold-change studyMold, crane/handling device, access openings, staging and complete travel envelope
Integrated cell layoutRobot, auxiliaries, guards, conveyors, material flow, operator and maintenance zones
Building route surveyDoors, turns, overheads, slab/bridge limits, temporary removal and final position
Utility coordinationPower, water, air, drains, exhaust/network where applicable, isolation and connection ownership
Approved lift/rigging planPrepared and approved by responsible qualified parties for the actual load, equipment, route and site conditions
As-built layoutFinal machine/cell position, services, access zones, changes and document owner
RELEASE SEQUENCE

Six gates move the layout from concept to as built.

This page is not a lift plan, foundation design, installation instruction or safe-work procedure.

01

Freeze the configuration

Identify machine, injection unit, screw/barrel option, guarding, robot, auxiliaries and shipping split before trusting dimensions or masses.

02

Review three envelopes

Separate transport, operating/moving and maintenance/removal envelopes; each can control a different part of the site.

03

Walk the complete route

Verify arrival, unloading, doors, turns, overheads, floor/bridge constraints, temporary staging and final placement.

04

Coordinate the foundation

Provide released support/load information to the qualified structural owner and return site requirements to the machine supplier.

05

Prove maintenance access

Use task-based access and component-removal paths rather than one generic clearance around the machine.

06

Control field changes

Record every changed position, anchor, trench, service entry, guard or access zone in the final as-built and acceptance files.

PRIMARY SOURCES / BOUNDARY

Controlled equipment data is an input to qualified site planning.

The official sources establish useful drawing and safety-context fields. They do not specify the future machine configuration or approve a destination-site plan.

ARBURG / OFFICIAL

Injection molding machine technical data

Supports requesting controlled technical data with setup and mold-installation dimensions for a selected configuration.

Boundary: ARBURG documents are examples of supplier-controlled inputs; no ARBURG dimension or configuration is transferred to this site.

US OSHA

Horizontal injection molding machine safety overview

Provides official safety context for horizontal injection molding machines and machine-access hazards.

Boundary: This buyer checklist is not a risk assessment, guarding design, lift plan, safe-work procedure or legal-compliance determination.

BUYER QUESTIONS

Layout, rigging and foundation FAQ

These answers keep supplier drawings, qualified site designs and final acceptance responsibilities separate.

01Is the overall machine footprint enough for a site layout?

No. Add moving envelopes, mold handling, robot and auxiliaries, operating tasks, maintenance/removal paths, logistics, guards, utilities and building access. Use the exact configured general arrangement.

02Can a supplier transport drawing be used as the lift plan?

No. It is an important load and handling input. Qualified responsible parties must prepare and approve the actual rigging/lift plan for the equipment, route, lifting devices, ground/building conditions and destination requirements.

03How much maintenance clearance should be allowed?

There is no universal clearance in this guide. Map each task and component-removal path using the configured machine instructions, tools, lifting method, site controls and responsible maintenance review.

04Does every injection molding machine need a special foundation?

Do not assume either way. Provide the exact machine support, load, leveling and dynamic information available to a qualified structural owner, who must assess the actual slab, soil/building, anchors, trenches and local requirements.

05What layout evidence belongs in the RFQ?

Send the site drawing and route survey, floor/building information, mold and handling data, desired cell equipment, utility entry constraints, maintenance/logistics zones and required configured-machine GA, transport and support drawings.

SITE PLAN / NEXT STEP

Send the building and handling constraints with the machine brief.

Attach the route survey, floor/site information, mold and handling plan, desired cell equipment, service/logistics zones and required configured drawing register.